FINNCHAIN SCRAPER SYSTEMS NOW INSTALLED TO NEW BLOMINMÄKI WWTP IN ESPOO

Currently a new wastewater treatment plant is being built in Espoo, Finland.
Finnchain has delivered and installed total 32 scraper systems for primary and secondary sedimentation. Installation was finished 06/2021 and plant should be operational during 2022.

  • “This project is a great example of Finnchain´s capability and experience of delivering large projects to a demanding environment, as the plant is located underground.
    We´ve done it many times before so I was very confident this one would be a success too.
    Co-operation with the main constructor YIT has been very smooth and easy, Ari Matti Multanen, Sales Manager at Finnchain, says.
  • Installation was done as scheduled, so we are very happy with Finnchain Oy,
    Santeri Saarikko, Project manager at YIT, explains. 

Installation year:           2020-2021
Tank type:                      Primary and secondary sedimentation
Tank size:                      Length     Width      No.
Primary                          46,0 m     9,65 m    8 pcs
Secondary                     52,5 m     9,65 m    24 pcs